Project Scope:

In April 2019, the Village applied for a State of Illinois Department of Commerce and Economic Opportunity (“DCEO”) grant to obtain funding towards the construction of new sidewalks in a residential neighborhood that currently has several small gaps in the sidewalk network. This sidewalk gaps project had previously been identified in the Village’s capital improvement program. The map below provides the new sidewalk locations.

SidewalkGaps

Construction Schedule

Start Date:

August 24, 2020

Targeted End Date:

September 18, 2020

Project Updates:

  • In April 2019, the Village applied for a State of Illinois Department of Commerce and Economic Opportunity (DCEO) grant. 
  • 03/03/20 - Village Board approved a resolution authorizing the Mayor to execute the DCEO grant agreement in the amount of $148,000.00.
  • 08/04/20 - The contract was awarded to Triggi Construction, Inc. 
  • 08/25/20 - The contractor began work this week on removals and framing. Concrete pouring is expected to begin early next week.
  • 09/03/20 - The contractor completed concrete pouring of the new sidewalks this week. Driveway and parkway restoration is scheduled to begin next week.
  • 09/11/20 - Driveway and parkway restoration was completed. This project is substantially completed.