W. Main Street Sidewalk Extension

SafeRoutes

Project Scope:

In April 2019, the Village was awarded the Safe Routes to School Grant for a sidewalk extension along W. Main Street. This project will fill in a gap in existing sidewalk between Cary-Algonquin Road and Briargate Road. Along with the sidewalk extension, the project will include the installation of a pedestrian safety island with warning beacon at Wulff Street. These safety improvements provide students a more accessible route to school without the need to cross at West Main Street at an uncontrolled intersection. The grant funding will pay for 100% of the construction and construction engineering costs.

Tentative Project Schedule:

Start Date:

09/01/2020

Substantial Completion Date:

10/30/20

Concept

Project Updates:

  • Village was awarded the Safe Routes to School grant in April 2019.
  • A local public agency agreement was approved by the Village Board on April 14, 2020, as well as an appropriation resolution on June 2, 2020.
  • A Lamp Concrete Contractors, Inc. was approved as the contractor on July 7, 2020 by the Village Board.
  • 09/03/20 - Utility relocation work has been completed. The contractor is scheduled to begin as soon as next week - the exact date is to be determined.
  • 09/17/20 - Contractor was on site this week preparing the layout for construction.